Monday, 24 December 2012

It fits....

The car looks good in the garage...

Merry Xmas to all and to all a good build!!


Thursday, 20 December 2012

We finally have keys

Zoom in (real dimensions: 1024 x 768)Image

So we have a heap of keys....... a few outstanding issues that will be fixed, SS told me if I left it on Master Key tradies could just go in to do stuff. I told him that the house is mine so no way I am leaving it on master key for anyone to just wonder in

I waited for a tradie to fix up an issue on the bath and then locked her up, a plumber arrived because he wanted to switch the bath spout to a shorter one but could not let himself in. Told him I'd have to run it past the boss so he'll be back next year for the dishwasher anyways.

Had a call from a sparkie trying to get in this morning "Can't get in, did you take the house off Master key".... hmmmmm yes

I'll be updating my blog over Xmas, I stopped because I got busted onsite and have a heap of pics to post of me being in there as per below ;)

Zoom in (real dimensions: 768 x 1024)Image

Tuesday, 18 December 2012

Handover date tomorrow

Well tomorrow is the final day that the Supervisor's at Allworth are working (Xmas party on Thursday)

Bathroom tiling should be completed today, tapware on tomorrow and a visit from Trend to sort out the rear door...

So hopefully tomorrow everything will be completed, I have told the SS I can visit the site in the afternoon to inspect. Fingers crossed it is all ok and I can get the keys, if not they are not back until the 14th January :(

Zoom in (real dimensions: 1024 x 768)Image

Thursday, 13 December 2012

SS contact

SS called the Boss today, all the items on the list have been resolved with the exception of the bathroom which is a work in progress.

Cleaners went through on Tuesday and will do another run through after the bathroom is done :)

Tuesday, 11 December 2012

Contact from the builder

Just had a call from home, the Deputy Construction Manager went onsite today.

He has emailed us to let us know that the items raised are being actioned, some have been completed and the rest are booked in to be resolved.

The Bath spout will be relocated to the correct position but this will push completion into next week some time due to the amount of work involved.

The house will be cleaned to "Industry Standard", so we are getting clarification on what that is....... aslong as it mean's the floor is vaccumed and cupboards, benches and wet area's all cleaned that should be OK

My wife was told by the GM it should be "like a shiny penny" when you walk in.

Good to see them onto everything, we have told them not to rush the work as we want it done right not fast.

Overall a little disappointing as we wont be able to get anything done until 2013 now :(


Monday, 10 December 2012

Leave cancelled heading back to work

Have been told by the GM that our complaints and concerns emailed have been forwarded to the Construction Manager for action.

Nothing back today so organised to head back to work tomorrow so I don't just sit at home playing PlayStation while we wait for them to finish

Sunday, 9 December 2012

Email to builder

Sent that email off yesterday, but this morning we were talking about the main bathroom. There was an issue with the spout not quite long enough to be fully over the bath. We were talking about the whole room seeming off.

So off to the display today and we see the problem. The display tap is on the end of the bath, our place has it in the centre on the long side.

So a please explain to the builder tomorrow. I am meant to be on leave to organise flooring installs etc but seems like I will cancel and head back to work Tuesday.....