Not a good day today......
Due to go in to sign the Building
Agreement tomorrow, called to ask if they had onsite parking and my CSO
asked if she had sent the final variation stuff i said no so through it
came.
First variation was Left side setback changed to 1.5m to
meet complying development guidelines....... Now i had been told early
Allworth required 1.2m even though i wanted 900mm. I let that go but to
lose now a total of 600mm from the side has got my blood boiling.
On the phone to the CSO spewing about it, asking why I was not told about this 3 weeks ago before it was submitted.
To
make matters worse if it went through council i would not be having the
issue, or if my block was 17.99m not 18m exactly it would not be an
issue under complying development.
The wife is upset as much as I
am, CSO said we can go back through council but when we go past our
tender period in 2 weeks we will be up for a $3600 increase and we would
have to pay the costs to send it to council (no idea how much).
The final option would be lose our deposit and walk away.........
Not happy campers today and really do not want to front in there tomorrow and sign.....