Had a call from the Head of Construction yesterday around 1pm, we have to an email to
request the window be removed and that the Private Certifier as
indicated they will look 'Favourably' at the request so fingers crossed
that means he will OK the change
So now the crisis over
The Certifier has agreed to delete the window with no requirement to go back through CDC
So
they will vary the plans and there will be no cost to us or refund. We
will be hit with a cost of variation for the Electricity though as there
is no junction box on our land so needs to come from the other side of
the block next door
All in all a happy afternoon, and my wife happy it is where she wanted it
No comments: